| Central Region High School #13 |
| CHPS Project in Progress |
|
School Information
|

|
|
School District:
|
Los Angeles Unified School District |
| Completed: |
N/A |
| Students: |
|
| Size: |
|
| Architecture Firm: |
HMC Architects
|
| CHPS Scorecard (2002 Edition) |
|
| Site: |
11 points |
| Water: |
2 points |
| Energy: |
8 points |
| Materials: |
3 points |
| IEQ: |
13 points |
| District Resolutions: |
5 points |
| TOTAL: |
42 points (mimimum of 28 points required of possible 81) |
| High Performance Features |
 |
- Community multipurpose room with separate entrace and restrooms for joint use of facilities
- Bioswale and filters for stormwater management
- Exceeds Title 24 by over 30%
- 75% of all construction and demolition waste to be recycled
- 90% meet the CHPS daylighting standard
- Building insulation, acoustic ceiling tile and carpet meet Section 01350 standards for low-emitting materials
- All classrooms have operable windows with lighting controls
|
| Back to CHPS Schools Page. |